Gross KPI
In SCOT, the Initial ORDER quantity and Planned Delivery Date (PDD) are considered for performance calculation. Order Updates are not considered
Gross performance reflects both Supplier and Metro combined performance
Gross performance KPI implies the performance before any root causes were assigned
Net KPI
Net performance KPI implies the Supplier performance after Root Cause Analysis (RCA)
Net performance reflects only Supplier performance
All Metro related issues are excluded from Net performance calculation
OTIF Calculation
The process of Gross to Net OTIF using SCOT
- We measure GROSS OTIF for our customers and we measure NET OTIF for our suppliers
For more details, refer to What is RCA1, RCA2 and RCA3