If you are a Project Leader or OBM Substitute and need to maintain or modify quantities on behalf of country buyers, please follow these main steps:
1. Disable the Emails and Reminders:
- If you do not wish to trigger automatic emails during this process, disable them. Skip this step if the grid is still online.
- Navigate to: Project Management > Emails and Reminders > Inform/Remind > Select All emails > Disable.
2. Extend the Demand Specification grid:
- Skip this step if the grid is still Online
- Navigate to: Demand Specification > Back to Tender Elements > Extend.
- Select the countries for which the structure should be extended and click Next.
- Insert a new deadline and click Apply.
3. Place values:
- Navigate to: Demand Specification > Back to Tender Elements > Place Values.
- Select the country for which you are maintaining the country quotation.
- Insert the values (you can also use Export and Import functionalities if there are many lines to maintain).
- Click Save and Publish All Tabs.
- The published values will appear in View Answerers.

4. Close the Demand Specification Grid:
- If the grid was extended only for this purpose, close it.
- Navigate to: Demand Specification > Back to Tender Elements > Close.
5. Enable the Emails and reminders
- Navigate to: Project Management > Emails and Reminders > Inform/Remind > Select All emails > Enable.